Sarasota Central County Water Reclamation Facility
Phase III Expansion

Project included design of an upgrade to the 480 volts power distribution and SCADA system that included an additional  FP&L utility transformers, a 480 volts-4000 A switchgear with provisions to synchronize two generators. Project also included upgrades to the existing generator, new 500 kW generator with sound attenuation, motor control centers, underground ductbanks, pumps with variable frequency (speed) controllers, and new programmable controllers.

 

Planning, Design and Engineering support of electrical power distribution systems 

2014 Gamboa Engineers